2024 Landslide Project, LS-17-25

2024 Landslides Project # LS-17-25


Contact: Fredrick Sturgis, Staff Engineer (513) 314-3431


Purpose/Need: This project will repair landslides on Hopper Hill Road (C-61), Baldwin Road (T-210), Coombs Road (T-414), and Moscow Cemetery Road (T-3096), located in Various Townships.


Action Necessary: Advertisement of Legal notice to obtain bids for this landslide repair project. The legal notice advertised in Clermont Sun on December 18, 2025, and also placed on the County website. Bid opening to be on January 15, 2026.


History of Project: All 4 landslides are similar with the following description: The landslide currently has an embankment failure causing a width restriction for the traveling public.  An application was filed with OPWC in September of 2023.  The OPWC application and agreement authorization was approved by Board on 9/13/2024 and the County Engineer executed the Grant Agreement on July 1, 2024.


Costs: The construction cost is estimated as follows:

ProjectRoad/TownshipTotal Project Amount
2024 Landslides
Hopper Hill Road (C-61)/Pierce Township
Baldwin Road (T-210) /Union Township
Coombs Road (T-414) /Washington Township
Moscow Cemetery Road (T-3096) /Washington Township
Project Cost$1,207,210.05

Expected Outcomes: Stabilize the existing landslides and repair the roadways on Hopper Hill Road (C-61), Baldwin Road (T-210), Coombs Road (T-414), and Moscow Cemetery Road (T-3096).


Time Period: Project is to be completed by July 31, 2026.


Responsible Department(s): County Engineers Office


Project Documents:

Legal Notice – PDF

Bid Results – PDF


Project Status:

Out for Bid