2022 Landslide Repairs, LS-08-23

2022 Landslide Repairs, Project #LS-08-23


Contact: Amanda J. Beiting, Senior Engineer (732-8874)

Purpose/Need: This project will repair landslides on the following roads located in various townships:


Wolfpen-Pleasant Hill Road

Old State Route 28 (2 slides)

Redbird Road

Sugar Camp Road


Action Necessary: Advertisement of Legal notice to obtain bids for this landslide repair project.  Advertising for a total of 2 weeks with the legal notice advertised on October 5, 2023, and also placed on the County website. Bid opening to be on October 19, 2023.


History of Project: All 5 landslides are similar with the following description: The landslide currently has an embankment failure causing a width restriction for the traveling public.  An application was filed with OPWC in September of 2021.  The OPWC application and agreement authorization was approved by Board on September 15, 2021, and the County Engineer executed the Grant Agreement on July 1, 2022.


Costs: The construction cost is estimated as follows:

ProjectRoad/TownshipTotal Project Amount
2022 LandslidesWolfpen-Pleasant Hill Road/Miami Township
Old State Route 28 #1/Goshen Township
Old State Route 28 #2/Goshen Township
Redbird Road/Miami Township
Sugar Camp Road/Miami Township
OPWC Grant
MVG Funds
Miami Twp Funds
Project Cost
$792,441.10
$140,062.65
$70,586.25
$1,003,090.00

Expected Outcomes: Stabilize the existing landslides and repair the roadways on Wolfpen-Pleasant Hill Road, Old State Route 28 (2 slides), Redbird Road, and Sugar Camp Road


Time Period: Project is to be completed by July 31, 2024.


Responsible Department(s): County Engineers Office.


Project Documents:

Legal Notice – PDF

Addendum 1 – PDF

Bid Results – PDF


Project Status:

Under Construction

2022 Landslide Repairs, LS-08-23