Contact: Doug Royer, Deputy Engineer (732-8885)
Purpose/Need: This project will replace/add approximately 2.5 miles of guardrail in various parts of the county.
Action Necessary: Advertisement of Legal notice to obtain bids for the project.
History of Project: This project has approved funding from the Ohio Department of Transportation. The project has gone through construction plan review through the Ohio Department of Transportation. We have now received Federal Highway Administration approval to go forward with the project.
Costs: The construction cost is estimated to be $300,000. ODOT will participate in 100% of the construction costs.
Expected Outcomes: Improved safety to the motoring public.
Time Period: The project will be completed within 120 days of the notice to proceed.
Responsible Department(s): County Engineers Office.